What’s a Realistic Budget and Timeline for a Kitchen or Bathroom Remodel If You Start in November?
When the temperatures drop and we’re all spending more time indoors, homeowners start searching for ways to make their spaces feel warmer, cozier, and more inviting. One of the biggest trends homeowners Google during winter remodeling season is interior wood finishes — especially accent walls, paneling, and custom carpentry that transform an ordinary room into a comfortable cold-weather retreat.
At The Highend Handyman, we’re seeing a huge rise in winter requests for wood-based interior upgrades. Here’s a breakdown of the most popular, high-impact carpentry projects trending right now — and why winter is the perfect time to start them.
🧮 Budget Basics: What Impacts the Price
Remodel costs vary based on your goals, the size of your space, and the materials you choose. Here’s how pricing typically breaks down:
1. Kitchen Remodels
- Basic Update: $20,000–$35,000
New countertops, flooring, and cabinet refinishing, but keeping the same layout. - Mid-Range Remodel: $40,000–$70,000
New cabinets, lighting, backsplash, and minor layout changes (like moving an appliance or sink). - High-End or Custom Kitchen: $75,000+
Full redesign with premium materials, custom carpentry, new layout, and high-end finishes.
2. Bathroom Remodels
- Basic Update: $10,000–$18,000
New vanity, flooring, fixtures, and paint — no plumbing relocation. - Mid-Range Remodel: $20,000–$35,000
Tile shower or tub replacement, upgraded lighting, new cabinetry. - Luxury Bathroom: $40,000+
Custom tile work, frameless glass shower, premium fixtures, and added features like heated floors.
💡 Tip: Material choices make a huge difference. A quartz countertop instead of laminate, or tile instead of vinyl, can shift your budget significantly. At The Highend Handyman, we help clients compare materials and finishes to make sure they get both quality and value.
⏰ Timeline: How Long It Really Takes
Remodels rarely happen overnight — and for good reason. A well-planned project prevents surprises and keeps the craftsmanship high.
Here’s a general timeline for projects started in November:
Kitchen Remodel
- Design & Planning: 2–4 weeks
(Selecting materials, confirming layout, ordering supplies.) - Demolition & Prep: 1 week
- Rough Work: 2–3 weeks
(Electrical, plumbing, framing, inspections.) - Finishes & Installation: 3–5 weeks
(Cabinets, counters, flooring, backsplash, paint.)
👉 Total: 6–10 weeks depending on scope and material lead times.
Bathroom Remodel
- Design & Material Selection: 1–2 weeks
- Demolition & Prep: 3–5 days
- Plumbing & Electrical Rough-In: 1 week
- Tile & Finish Work: 2–3 weeks
- Final Touches: 1 week
👉 Total: 4–6 weeks on average.
Because you’re starting in November, you’re working in a sweet spot — just after the busy summer rush, and before most contractors’ spring schedules fill up. That means better availability, more focused attention, and often shorter lead times.
🧰 Why Starting in November Makes Sense
Here’s what makes a late-year remodel smart:
- Contractor flexibility: Schedules often open up after exterior projects wind down.
- Material discounts: Suppliers sometimes offer year-end pricing or clearance on popular finishes.
- Weather advantage: Indoor projects aren’t affected by cold or rain — work stays on track.
- New-year ready: You’ll start 2026 with a fresh, functional space.
🪚 How The Highend Handyman Can Help
We specialize in quality craftsmanship and clear communication — from the first walkthrough to the final cleanup. Our team handles carpentry, drywall, electrical, and painting under one roof, so your remodel runs smoothly without juggling multiple contractors.
When you work with The Highend Handyman, you’ll get:
- Transparent estimates with no surprise charges
- Realistic timelines that respect your schedule
- Clean, respectful work on every jobsite
- Results that balance function and style
🏠 Ready to Get Started?
If you’ve been thinking about upgrading your kitchen or bathroom, now’s the perfect time to begin planning. You can enjoy a smooth, on-schedule remodel that’s complete before spring — and add lasting value to your home.
📞 Contact The Highend Handyman today for a consultation, and we’ll help you design, price, and schedule your remodel with confidence.